1 . PRE-OPENING OFFICE

筹建办公室

a) Introduction

简介

Depending upon type of hotel and location, hotel staffing commences as early as ten months prior to opening, in order to facilitate the start-up of hotel operations. Off-site offices will be required in order to house the pre-opening team consisting principally of Sales, Marketing, Human Resources and Executive Administration. These offices are required until the hotel is ready for occupancy (normally six months before soft opening). Although temporary, the offices are to be fitted-out and to function so as to fully support, without compromise, all office requirements. Included in this section is a generic pre-opening office schedule, which will be customized for the specific hotel project.

为推动酒店顺利启用,酒店可提前开展人员配置工作;根据酒店的类型与所处位置的不同,最早在开业前10个月即可开始。在酒店可以进驻办公(大约在试营业前6个月)前,需要一些场外办公室来安置主要由销售、营销、人力资源管理和行政管理人员组成的筹建工作组。虽然这些场外办公室只是临时性的,但应装备齐备、运作良好,完全满足(不打折扣)各种办公要求。本节是通用的筹建办公室方案,可根据酒店项目的具体情况加以修改。

b) Site

地点

Pre-opening offices shall be located adjacent, or as close as possible, to the hotel site. Proximity to the model room, for ease of access by Sales and Marketing personnel, is also beneficial.

筹建办公室应毗邻酒店所在地,或尽可能地与之接近。样板房靠近筹建办公室,便于销售和营销人员使用,也是有利的。

c) Area

办公面积

A typical pre-opening office requires approximately 295 m2 (3,215 ft2) based on a 300-room hotel. Add approximately 20% for circulation.

一般而言,有300个房间的酒店大致需要295平方米3,215平方英尺)的筹建办公室。外加大约20%的走动空间。

d) Parking

停车设施

Provide an equal number of parking spaces to adequately accommodate pre-opening staff. Provide no less than twenty staff parking spaces, with five additional spaces for visitors. Parking area shall be well illuminated for maximum security, consistent with illumination levels described in the Design Standards.

要提供足够筹建人员使用的车位数量。提供不少于25个职员用车位,另加5个访客用车位。停车区域的照明要充足,能提供最高的安全保障,并与本设计标准中要求的照明水平一致。

e) Washrooms

洗手间

Provide a minimum of one female and one male washroom, designed in accordance with local code requirements. Include a separate janitor’s closet with sink.

提供至少一个男洗手间和一个女洗手间,要按照当地法规的要求设计。

f) Lighting and Finishes

照明与装饰

All floors shall be carpeted, with the exception of the washrooms, pantry, fax/copy and storage areas, which are to be finished in vinyl composite tile. Walls to be painted drywall. Ceilings to be acoustic tiles. Provide satisfactory general lighting. Additional task lighting required at each workstation. Office areas to be separately switched.

除洗手间、茶水间、传真/复印室和储物区的地板铺乙烯基复合地砖外,所有地板都要铺地毯。墙壁是上漆的干砌墙。天花板使用吸声瓦。提供令人满意的普通照明。每个工作区另加工作照明。办公区的电源单独设置开关。

g) Reception

前台接待

Small reception and waiting area to be provided near the entrance. Reception area layout to be visually separate from the balance of office space. Provide comfortable lounge furniture in the waiting area, with a telephone.

在办公室入口附近安排一个小的接待和等候区域。接待区域与办公室的其它部分不能相互望见。在等候区安排舒适的长沙发,并配电话。

h) Beverage/Pantry Area

饮料与茶水室

A small pantry area of approximately 5 m2 (55 ft2) is to be provided complete with full size refrigerator, sink with counter and cabinets above and below.

安排一个小茶水间,面积约在5平方米55平方英尺),内放全尺寸的冰箱;带洗手台,台上台下有壁柜。

i) Stationery/Copying

文具/复印

A separate room requiring approximately 10 m2 (110 ft2) is to be provided to accommodate mail, copying, shipping and receiving functions. Copy area should include a counter with upper and lower cabinets (50% lockable). Equipment to include full size copy machine, fax machine, postage machine and a wall-mounted telephone.

安排一间独立的大约10平方米110平方英尺)的房间作收发邮件及物品、复印之间。复印区包括一张案台,台上台下要有厨柜(一半上锁)。室内的装备有全尺寸复印机、传真机、邮资机和挂壁式电话。

j) Temporary Telephone Switch

临时电话总机

Provide small PBX (PABX), or hybrid key system (e.g. Nortel Option 11, or Norstar 2), with thirty extensions and thirty central office lines with voicemail. In addition, provide separate lines for fax and modem. Central office service may be provided by a digital connection (T1 or E1) plus eight analog circuits. Optionally, a thirty-two analog circuit configuration is acceptable. Coordinate switch selection with local service provider and Four Seasons.

提供小型的专用分组交换机(专用自动交换分机)或数字电话交换系统(比如Nortel Option 11,或Norstar 2,要有30条分机线、30条中继线,并带语音邮件功能。另外,为传真与调制解调器单独配置线路。中继服务可由一个数字电路(T1E1)加8个模拟电路完成。另外也可选用配置32个模拟电路的方案。应与当地服务提供商和四季酒店协调选择总机事宜。

k) Internet

互联网

Provide two ISDN or two DSL internet connections from local internet service provider. Connection is to be terminated at a switch and routed to each individual workstation as per hotel configuration requirements, to be reviewed with Four Seasons prior to installation.

从当地网络服务提供商处获取2ISDN2DSL网络接入线路。按照酒店配置要求,网络连接接入总机,然后经路由器分至各个独立的工作区;接线前四季酒店要先进行检查。

l) Power and Cabling

电源与配线

Provide the equivalent of three simplex power outlets and one voice data outlet at each workstation. Each workstation will require one voice and one data outlet. Each administrative assistant workstation and reception to be provided with two voice and two data points. All cabling to be terminated in a wiring closet located within the secured Four Seasons area. Wiring closet to be large enough to mount telephone switch, computer switches and two servers. Provide six duplex power outlets for this equipment. Incoming telephone and internet service should terminate in this room.

为每个工作区提供三个单工电源插座及一条声音/数据线。每个工作区要配1条声音线、1条数据线。 每一个行政助理的工作区和接待区要配2条声音线、2条数据线。所有配线接入位于四季酒店安全区域内的配线柜。配线柜的要足够大,能容纳电话总机、计算机电源开关和两台服务器。为此设备配置6个双工电源插座。 打入的电话的网络服务以此房间为终端。

m) Typical Pre-Opening Office Area Requirements

筹建办公室的一般面积要求


2. HANDOVER PROCEDURES

酒店移交程序

a) Owner’s and Contractor’s Responsibilities

业主与承包人的责任

As construction approaches substantial completion, Four Seasons shall be provided with the following information:

在建筑接近实际竣工时,须向四季酒店提供以下信息:

i) Construction completion and handover schedule

建筑竣工及移交安排

ii) Deficiency inspection schedule

缺陷检查安排

iii) General

一般信息

Equipment spare parts list

设备零部件清单

Schedule of all equipment identification tags

所有设备的识别标签

Key schedules

密钥安排

Paint colour and material schedules

油漆颜色及材料

Proprietary product names and suppliers

专利产品的名称及供应商

Warranties/bonds

质保

Attic stock

备用料

List of all service suppliers and equipment vendors

服务提供商及设备供应商名录

Balancing and commissioning reports for all mechanical, electrical, plumbing and life safety

Systems

所有机械、电气、水暖和救生系统的调试运行报告

Training schedules

培训安排

Equipment maintenance schedules

设备维护安排

iv) All documentation as noted in the substantial completion documentation section (B-9) of these standards.

所有在本标准的实际竣工文件部分(B-9)中写明的文件。

Owner is responsible to ensure that Contractor prepares a deficiency inspection schedule which reflects the mutually agreed handover schedule dates and provides adequate time for the building team to inspect deficiencies, complete remedial work and re-inspect. Given the size of most properties, this is a long and complex process, which requires detailed planning and disciplined implementation.

业主应负责确保承包人准备一份缺陷检查计划,此计划应符合各方同意的工程移交时间表,并给建筑工程队留下足够的时间进行缺陷检查、修补和再检查。考虑到大多数酒店的规模,这将是一个漫长而复杂的过程,需要详尽的计划和严格实施。

At the outset of deficiency inspection, Four Seasons shall participate in the inspection process with Owner’s building team, to establish an inspection protocol and set a quality standard which is then applied to the balance of the property by the building team (Owner representatives, Architects, Interior Designers, mechanical, electrical, plumbing and life safety Consultants and Contractor representatives). The building team is responsible to manage the process.

在缺陷检查开始时,四季酒店将与业主的建筑工程队一同参与检查,确定检查的方案和质量标准,作为业主的建筑工程队(由业主的代表,建筑师,室内设计师,机械、电气、水暖和求生顾问,以及承包人的代表组成)对余下部分进行检查的依据。建筑工程队负责管理此进程。

Contractor is responsible for preparing detailed, itemized inspection templates for guestrooms, public and back of house areas as well as building exterior and landscaping. Contractor to enter all deficiencies into a tracking computer program to allow sorting by sub-trades and efficient follow up during the re-inspection phase.

承包人负责为客房、公共区域、后勤区域、建筑外观和景观美化部分制定详尽的、逐项的检查模板。承包人将所有缺陷输入计算机的跟进程序,以便分类并提高复检阶段的工作效率。


3. TRAINING SCHEDULE

培训安排

Certain areas of the of the hotel are required in advance of others. It is common for Four Seasons to agree to a joint occupancy with the Contractor during construction. The following timeline identifies which areas are required. All areas turned over by Contractor must be complete, safely accessible and with fully functional MEP and life safety devices.

酒店的某些区域需要比其它部分更早地投入使用。四季酒店通常会同意在酒店建筑期间即与承包人一起进入酒店。以下时间表指明了酒店的哪些区域是要提前使用的。承包人移交的所有区域都必须是已完工的、出入是安全的,并且机械、电气、水暖及求生设备运作工常。


4. FF+E INSTALLATION AND OCCUPATION

家俱、固定装置与设备(FF&E)的安装和酒店使用

a) General

概要

Four Seasons will be permitted to occupy the building in stages as outlined in the turnover timeline (section

B-4) for the purposes of installing FF&E.

四季酒店应被允许在移交时间表(B-4节)中所列各阶段中进驻酒店,安装家俱、固定装置与设备(FF&E)。

Contractor will be responsible for providing the Four Seasons FF&E team with the following services at no cost during the FF&E installation program:

承包人应在家俱、固定装置与设备(FF&E)安装期间免费为四季酒店的FF&E工程队提供以下服务:

i) Heating, cooling and humidity control as required to protect the FF&E.

提供为保护FF&E所需的加热、制冷及温度控制。

ii) Temporary lighting.

临时照明。

iii) Complete construction clean of all areas of the building prior to handover including interior and exterior glass, all finishes, vacuuming all floors, polishing all mirrors, chrome and plumbing fixtures.

在移交前清理所有区域,包括内外玻璃,所有装饰,用吸尘器打扫地板,擦亮所有镜子、镀铬物制品和水暖接头。

iv) Removal of all packing cases, boxes, wrapping, off cuts and all other associated debris brought into the building by the FF&E installation team.

清理掉所有货箱、盒子、包装物、边脚料及建筑物内其它由FF&E安装工程队的工作而产生的碎片。

v) Exclusive use of at least two elevators during normal working hours and exclusive use of at least three elevators at all other times, including providing necessary elevator operators.

在正常工作时间内,FF&E工程队要独用至少两部电梯,在其它时间至少三部电梯;并应配备必要的电梯操作员。

vi) A turnover timeline is included in the previous section, clearly indicating when areas of the hotel must be complete and turned over to Four Seasons by the Contractor for FF&E installations and operational training.

上一节中的移交时间表清楚写明了承包人要完成酒店的哪些部分并移交四季酒店以作FF&E安装和酒店运作培训之用。

b) Installation and Occupation Requirements

安装与酒店使用的要求

i) Areas offered for FF&E installation and occupancy must achieve construction completion prior to acceptance by FSH. Construction Completion means that the specific area is fully operational and free of tradesmen, 100% complete with all deficiencies corrected and accepted by the Owner for installation of FF&E. Areas offered for acceptance must include completion of all MEP systems, including all system balancing and commissioning necessary to support occupancy of the area for the purposes of FF&E installation and training. Testing and certifying of all specialist equipment such as the kitchen, laundry, valet and other specialist equipment by consultants and local authorities is also required prior to acceptance.

FSHR接收前,所有移交并用于FF&E安装和使用的区域都必须完成建筑工作。完成建筑工作是指所涉区域能完全运作,工人撤出,所有缺陷修补完毕,业主认为可交付进行FF&E安装。 所提交验收的区域必须完成所有必要的MEP(机械、电气、水暖)系统工作,包括为系统的协调和试运行,以支持使用这些区域进行FF&E安装和培训。在提交验收前,需由顾问及当地机关对所有特种设备(厨房、洗衣房、衣架等)进行测试与认证。

ii) Where an area includes equipment, including specialist equipment supplied and installed under

an FF&E contract, all equipment must be connected, tested and fully operational when turned

over to Four Seasons, including:

在移交给四季酒店前,如某一区域有因FF&E合同而安装的设备(含特种设备),这些设备必须经通电测试,应能完全运作。这些设备包括

a) Food and beverage equipment

食品及饮料设备

b) Laundry and valet equipment

洗衣及挂衣设备

c) Computer equipment

计算机设备

d) Telephone equipment

电话设备

e) Garbage compaction equipment

垃圾压实设备

Contractor is responsible for coordinating with the specialist equipment Contractors and Four

Seasons to ensure these requirements are met.

承包人应负责与这些特种设备的供应商和四季酒店协调,保证符合以上要求。

iii) Entire guestroom floors must be turned over at one time, including all guestrooms, corridors,

suites and service areas.

客房楼层必须一次性移交,包括所有客房、走廊、套房和服务区。

iv) A fully detailed turnover program detailing individual areas will be prepared and coordinated with the Contractor, nine months prior to opening and will include FF&E staging areas, FF&E access routes and security measures.

在试营业9个月前,将制定(并与承包人协调)一份详尽的移交计划,对个别区域进行详细说明,并将包括FF&E的安装区域、FF&E安装时的出入路线及安全措施。

v) It is Owner and Contractor’s responsibility to obtain all necessary temporary or partial occupancy certificates.

业主和承包人负责处理临时驻入或部分使用酒店所需的证件。


5 . TURNOVER AND DEFICIENCY PROCEDURES

工程移交与缺陷检查程序

a) Summary

概要

The purpose of this section is to provide direction in expediting the turnover process of guest floors from Contractor to Owner for the installation of FF&E. Owner must give Contractor the information required to complete the guest floors to a quality standard Four Seasons can accept. By establishing these standards and criteria with Owner and Contractor well in advance of turnover, it is likely that most deficiencies can be corrected during the initial inspection and remedial work period, thus allowing Owner to accept rooms that will require minimal additional work to achieve Four Seasons Perfect Room Standards.

本节的目的是提供指示说明,以加快承包人将房客楼层移交给业主进行FF&E安装的过程。业主必须给予承包人完成四季酒店能接受的客户楼层所需要的信息。在移交前早早与业主和承包人确定这些标准与尺度,可使大部分缺陷在初次检查和修补期间内得到更正,这样业主接收的房间只需经过最少量的额外加工即可达到“四季酒店完美房间标准”。

The review and acceptance process has Owner, Architects and various Consultants inspecting the guestrooms and corridors to identify deficiencies or variances to the project specifications. A deficiency list is developed and issued to Contractor for action. This deficiency list becomes a road map for Contractor and, once complete, allows Owner to accept the room for the installation of FF&E.

在验收过程中,业主、建筑师和顾问检查房间和走廊的缺陷或与工程规格说明不相符之处。制作一份缺陷表交给承包人进行改正。此缺陷表是承包人工作的路线图,改正工作完成后,业主即可接收房间进行FF&E安装。

Upon completion of the FF&E installation, Owner offers the room to Four Seasons for final acceptance. The Four Seasons operations team then re-inspects the room and issues a second deficiency list which Owner will cause Contractor to correct. This does not include damage to the room as a result of this FF&E installation. Repair to rooms that have been damaged by the installation of FF&E is handled as a separate repair program by Owner and would be a billable repair by Contractor.

FF&E完成后,业主将客房交给四季酒店最后验收。四季酒店的工作组在对房间再次进行检查后再开出一份缺陷表,交给业主并由其督促承包人改正。此缺陷表不包括因FF&E安装而造成的损毁。修补因FF&E安装而受损的房间由业主另行安排,如由承包人修补将另行计费。

b) Control Room

控制室

Contractor shall finish the first available standard guestroom and Four Seasons Executive Suite in the hotel as control rooms. These rooms will be finished as soon as possible in advance of the general construction program. This will allow sufficient time for the review and approval of the complete installation inclusive of mechanical, electrical and plumbing (MEP) infrastructure and connections, construction assembly, architectural and interior finishes. These control rooms serve as a benchmark for the quality of construction

for the balance of guestrooms and suites.

承包人应首先完成一个标准客房和一个四季酒店行政套房作为控制室之用。这些房间应在建筑工程全面完工之前尽早完成。完成这些房间将为审核房间里所有安装的设施提供足够的时间,这些设施包括机械、电气与水暖(MEP)系统的基础部分与连接,建筑总装,建筑物及室内的装饰等。控制室将作为余下客房和套房建造的质量标尺。

The control room, once completed and approved for its architecture, finishes, MEP and FF&E, shall serve as the standard that Contractor must meet in all guestrooms. The deficiency review process shall focus on variances in the guestrooms being turned over from the approved control room. Where the guestroom offered for acceptance conforms substantially to the control room architecturally, the deficiency inspection

should be limited to finishes, FF&E and MEP items.

控制室完成且其建筑结构、装饰、MEPFF&E经验收后,将成为承包人建造所有客房要达到的标准。对移交的客房进行缺陷评议时,将主要检查与已验收的控制室之间的差别。如果提交验收的客房在建筑结构上与控制室基本相同,则缺陷评议主要检查装饰、FF&EMEP

c) Procedures

程序

The Hotel Director of Engineering, the Four Seasons Design & Construction Manager and FF&E Coordinator will all participate in the initial deficiency review of a representative control guestroom along with the Owner’s representatives, the Architect, Consultants and contractor. The purpose of this joint effort is to establish a standard for both Contractor and Owner’s representatives who will perform the deficiency inspections.

酒店的工程总监、四季酒店设计与建造部门的经理及FF&E协调员将与业主代表、顾问和承包人一起参加对控制室(客房)的首次缺陷评议。如此联合行动的目的是为负责缺陷评议的承包人和业主代表确立评议的标准。

A deficiency list will be developed and given to Contractor for action. Frequently, a review of this type will not only identify certain deficiencies unique to the control room but will also highlight common deficiencies found in each room. The intent of the control room review is to establish the benchmark that Owner and Four Seasons mutually agree as well as identifying common deficiencies.

评议后的缺陷表将交给承包人进行修补工作。通常,缺陷评议不仅应检查所评议的房间与控制室的不一致之处,还应关注各个房间的共同缺陷。对控制室进行评议是为了确立业主与四季酒店都同意的质量基准,并找出房间的共同缺陷。

Once the deficiency list for the control room is established, Contractor shall work to correct the deficiencies

and then re-offer the room for a final review and acceptance. Concurrently, the Contractor’s quality control

team should be working to correct the common deficiencies identified in all other rooms that are substantially

complete. It is the intention of this program that Four Seasons participate in the initial deficiency review of

about 5% of guestrooms.

一旦控制室的缺陷表完成,承包人应修补缺陷并提交房间作最后验收。同时,承包人的质量控制组应修补所有其它已实际完工的房间里出现的相同的缺陷。本计划的设想是四季酒店在初次缺陷检测中参与大约5%房间的检查工作。

The tools required for deficiency review are:

缺陷检查工具有:

Construction drawings and specifications

结构图及规格说明

Small torpedo level

鱼雷型水平尺(小型)

Electric socket tester

电源插座检测器

Tape measure

卷尺

Guestroom checklist

客房检查清单

The room will be reviewed from two perspectives; architectural fixed décor and mechanical, electrical and plumbing systems.

对房间的检查从两个方面进行:建筑中的固定装饰,以及机械、电气和水暖系统。

All deficiencies are to be detailed in written format according to the above categories. Each item is to be numbered and the deficiency clearly identified referring to the construction drawings and specifications as necessary.

所有缺陷要按照以上分类作书面记录。每一缺陷都要编号,利用结构图和规格说明明确指出每一缺陷的所在。


6 . CONSTRUCTION COMPLETION

建筑完成

Construction completion permits the soft opening of the hotel. A Four Seasons Hotel soft opening will require all areas of the hotel, support facilities such as staff housing, pools, landscaping, etc. to be complete, including deficiency correction, FF&E installation and training finished, with the possible exception of some guest rooms. Hence, soft opening can be defined as the point in time when all pre-opening activities are concluded. From a construction point of view, the pre-opening period consists of three milestone events for each area of the hotel:

建筑完工后酒店才可进行试营业。四季酒店的试营业需要使用整个酒店;酒店的配套设施,如员工宿舍、泳池、景观美化等必须完工,缺陷得到修补,FF&E安装完成,培训结束;但某些客房可作例外处理。因此,试营业开始的时间就是所有筹建工作完成的时候。从建筑工程的角度来看,酒店里每一部分的筹建期均包含三个阶段:

a) Construction

建筑

The first is that construction is completed, deficiencies rectified and the area in question is turned over for FF&E installation.

第一, 建筑工作完成,缺陷已改正,所涉区域已移交作FF&E安装用。

b) FF&E Installation

FF&E安装

The second is that FF&E installation is complete and the area in question is turned over for training.

第二,FF&E安装完成,所涉区域已移交作培训用。

c) Training

培训

The third and last is that training is complete for all areas during the pre-opening and hotel is ready to be

operated in a “soft opening” mode.

第三个也是最后一个是,筹建期间各区域的培训结束,酒店可进入试营业。

The Four Seasons philosophy is that guests must receive a level of service equivalent to a hotel that has been in operation for years. The soft opening mode, which is likely about two months long, is that operating period of time when Four Seasons controls the number of hotel guests and restaurant patrons and, hence, effectively controls their experience. As an example, initial operation of the restaurants limits the number of covers to 25% of capacity. The number of covers is increased gradually as the staff demonstrates the ability to provide appropriate service. The same approach applies to the guestrooms. When management determines that staff is adequately trained to operate the hotel at 100%, then the soft opening period has concluded and a “hard opening” is achieved, which coincides with the “Grand Opening” party.

四季酒店的理想是酒店顾客享受到的服务水平应与运营多年的酒店的服务水平相当。试营业期间(大约2个月),四季酒店将控制住客和使用酒店餐厅的人数,以保证他们在酒店里的体验。比如,在开始的时候,餐厅将用餐人数控制在总容量的25%左右。随着员工表现出他们的技能足以提供适当的服务,这个比例将逐渐提高。同样的策略也将应用于客房方面。如管理层认为员工已得到足够的培训,能运作整个酒店时,试营业结束,迎来正式开业,并举行开业庆典。

While the soft opening may also appear as a training period, it is not to be confused with the specified training time during the pre-opening. The soft opening period is where staff refine the skills learned during training and develop their confidence to operate at full capacity.

虽然试营业似乎也是一种培训,但这不应与度营业期间进行的专门培训相混淆。试营业期里,员工将完完善他们在培训中学到的技能,并树立起运营整个酒店的信心。


7. TESTING, ADJUSTING, BALANCING AND COMMISSIONING

测试、调整、协调和试运行

a) General

概要

Contractor is required to provide the following services:

承包人应提供以下服务:

i) All Heating, Ventilation and Air Conditioning (HVAC), electrical and voice and data systems

are required to be adjusted, balanced and commissioned by a licensed and independent

Commissioning Consultant. Commissioning work shall not commence until all systems and

inter-related systems are substantially complete.

所有供暖, 通风与空调(HVAC)系统、电气系统、声音/数据系统都需经独立的试运行顾问进行调整、协配和试运作。试运作应在所有这些系统和相关系统实际完工后进行。

ii) Contractor is to engage and pay for the services of an independent HVAC testing agency to

perform the work as specified in part II of these Standards (Mechanical, Electrical and Plumbing

Standard). The testing agency is to be a firm regularly engaged in the testing, balancing, adjusting

and commissioning of heating, ventilation and air conditioning (HVAC) installations. The testing

agency shall be subject to the approval of Four Seasons but will report directly to Owner or his

representative. The approved testing agency shall have industry standard qualifications and

should provide a copy of current license and certificates.

承包人负责联系独立暖通测试机构进行本标准第二部分(机械、电气及水暖标准)中所列各项工作,并对其服务支付报酬。此检测机构应是经常从事供暖, 通风与空调((HVAC)系纺的测试、协配、调整、试运作的机构。测试机构的选择必经四季酒店批准,但其直接向业主或业主代表负责。经批准的测试机构应具有行业从业资格,并要提供有效的许可证和证书的副本。


8 . SUBSTANTIAL COMPLETION AND CLOSE OUT DOCUMENTATION

实际完工与项目完工文件

a) Substantial Completion Documentation

实际完工文件

Three months prior to substantial completion, Four Seasons shall be provided with the following:

在实际完工前3个月,应向四季酒店提供以下材料

i) Two sets of operating and maintenance manuals for all mechanical and electrical equipment.

The manuals shall include shop drawings, descriptive and technical data, maintenance and

operating procedures, wiring diagrams, spare parts list, local suppliers for spare parts, and local

service representative contact information. Manual shall be assembled in 2” black loose-leaf

binders clearly identified as to their contents. Electronic copy of all above documentation to be

provided as well.

各机械及电气装备的操作和维修手册各两份。手册内应包含施工图、说明性的和技术性资料、维修与操作程序、电路图、零件清单、当地零件供货商及维修机构的联系信息。手册将用2英寸厚的黑色活页文件夹装订,文件夹上写明文件名称。另还须提供以上文件的电子版本。

ii) Two sets of manufacturers recommended maintenance procedures for all architectural and

interior design materials. Each set of maintenance procedures shall be bound and indexed in a

loose-leaf folder. Electronic copy of maintenance procedures to be provided as well.

制造商推荐的建筑及室内设计原料的维护程序两套。每一套程序均用活页文件夹装订,并做索引。另还须提供维护程序的电子版本。

b) Completion/Close Out Documentation

工程完工文件

Upon substantial completion, Four Seasons shall be provided by Owner/Contractor with the following

maintenance information:

在工程完工时,业主/承包人须向四季酒店提供以下关于维护的信息:

i) Two sets of architectural, mechanical, electrical and interior design as built drawings. Drawings

shall be on mylar and shall be individually bound and clipped in sets. Electronic copy of all

drawings to be provided as well.

建筑、机械、电气和室内设计的竣工图纸各两份。图纸印在麦拉片(mylar)上,分门别类,单独装订。另还须提供以上图纸的电子版本。

ii) Two bound summaries of all sub contracts awarded on the project, detailing type of sub-contract

and indicating the name, address and telephone number of each sub-contractor. Electronic

copy of above contact information to be provided as well.

两册装订好的分包商概要,记载所有参与工程的分包商的类别、名称、地址、电话号码。另还须提供以上联系信息的电子版本。

iii) Two bound copies of all architectural and interior design material specifications used in the property, including small samples. This document is intended to allow patch and repair work by Four Seasons maintenance to conform to the original specifications for best blending effect.

所有工程建筑和室内设计中使用过的原材料(包括小样)的说明文件的复印件,装订成两册。这些文件将便于四季酒店在进行维护修补时选用与原规格说明一致的材料,取得最佳的修补效果。

iv) Two framed valve charts listing each valve by number, system and function.

两份框裱阀门图,列明有阀门的编号、所属系统和功能。


9 . GUARANTEES AND WARRANTIES质保

a) General概要

Contractor shall guarantee the building free from defects for a period of not less than one year with the

exception of the items included in these Standards for which a longer guarantee period is specified.

承包人应保证建筑在不短于1年的时间内不出现故障;对于要求更长质保期的部分,本标将准确定质保时间的期限。

b) Standard Warranties

标准质保期

All systems and equipment are to have a one-year warranty except as noted below. Warranties are to

commence on the date of soft opening and to continue for a period of one year. Contractor is to make

allowance for systems and equipment being put into service for the purpose of beneficial use prior to soft

opening. In no case is the warranty period to begin prior to the hotel opening. Warranties shall include all

replacement parts and labour. Emergency service shall be provided at no cost during normal working hours for the duration of the warranty period. After hours service is to be available with the premium portion being a billable item at prevailing local rates.

除下文提到的部分,所有系统和设备的质保期为一年。质保期为从试营业开始后的边续一年。在试营业前因需要而投入使用的设备与系统,承包人要为它们预留质保时间。但无论无何,质保期的起计时间不得早于酒店开业的时间。质保应包括零部件和劳务在内。在质保期内,正常工作时间里的紧急抢修服务应无偿提供。下班后的维修服务,其超出部分按当地通行的标准支付。

c) Extended Warranties

延长的质保期

Extended warranties must be co-signed by Contractor and Sub-Contractor/Supplier. Commercial

refrigeration and air conditioning compressors are to have an additional four-year warranty period, which

covers the cost of any replacement compressor. Labour shall be billable at prevailing local rates.

延长的质保期由承包人和分包人/供应商共同承担。商业冰箱和空调的压缩机的质保期须额外延长四年,质保内容覆盖更换压缩机的成本。劳务费按当地通行标准支付。

Internal waterproofing systems are to have an additional two-year warranty period, which

covers all costs to repair or replace any failed system.

建筑物内部防水系统的质保期须额外延长两年,质保内容覆盖对故障系统进行维修和更换的所有成本。

Roofing systems are to have an additional nine-year warranty period, which covers all

costs to repair or replace any failed system.

屋面系统的质保期须额外延长九年,质保内容覆盖对故障系统进行维修和更换的所有成本。

Windows and curtain wall (exterior cladding system) are to have an additional four-year

warranty period, which covers all costs to replace any failed units.

窗和幕墙(外立面)的质保期须额外延长四年,质保内容覆盖对故障单位进行更换的所有成本。

d) Warranty Notice Database

维修通知数据库

The Warranty Notice Database is a post opening device designed to track deficiencies and warranty issues

that arise during the first year of operations (during the one year warranty period after opening).

维修通知数据库,是酒店开业后设计用于跟踪酒店在第一年营运中(也即开业后一年的质保期内)出现的缺陷及维修通知的。

The database is customized to each property and is managed by the Director of Engineering and can be

copied to others at his/her discretion. Home office has access to the database as well. The notices are

issued post-opening.

每个酒店的数据库都是度身订制的,由工程总监管理;工程总监可视情况将数据拷贝给他人。总公司也可使用此数据库。开业后签发各维修通知。


10. SERVICE CONTRACTS

服务合同

a) General Note

总则

Owner shall ensure that Contractor has all Sub-contractors prepare the following service contracts. All

contracts listed below are to be based on scheduling as determined by hotel operations, based on area

availability. Provide emergency service during normal working hours at no additional cost. Allowances to

be included for after hours service. Alternatively, after hours emergency service may involve a premium

portion, which is billable.

业主应确保承包人让所有分包人准备以下服务合同。下列合同均取决于酒店运营的时间安排和场地的可用性。在正常工作时间内提供紧急维修服务不得收取额外费用。下班后的维修服务有津贴。另外,下班后的紧急维修也许有超出时间的部分,这部分的服务是有偿的。

b) Pest Elimination

杀虫

Provide a full clean-out of the facility prior to the installation of FF&E. Provide twice-weekly service or as

frequently as required if pests are evident for a period of one year after soft opening. Allowance should be

made for on going service to be performed after normal working hours during the first year of operation.

在安装FF&E之前,要对设施进行全面的大清理。在试运营开始后1年的时间内,每两周进行一次杀虫,如出现虫害的迹象,则按要求经常杀虫。在营运后的第一年里,在正常工作时间之外继续进行的维修服务有津贴。

c) Metal Maintenance and Restoration

金属器件维护与复位

Provide for refinishing and restoration of all architectural and decorative metals after the installation of FF&E but prior to soft opening. Provide monthly cleaning of all architectural and decorative metals for a period of one year after soft opening. Prior to the end of the contract period all architectural and decorative metals are to be refinished as required. Metals subject to wear and tear such as entrance doors and elevator cab interiors shall have allowances to be refinished twice during the one-year period.

FF&E安装完成后、试营业前对所有建筑金属件和装饰金属件进行表面修整并复位。试运营开始后1年的时间内,每月对所有建筑金属件和装饰金属件进行一次清洁。在合同结束前,所有建筑金属件和装饰金属件要按要求进行表面修整。容易受到磨损的金属件,如进出口门和电梯间内部,在第一年里应多做两次表面修整。

d) Marble and Stone

大理石与石材制品

Provide for polishing and refinishing of all interior architectural and decorative marble and stone prior to

installation of FF&E. All materials are to be brought back to their specified condition. Provide monthly

polishing or honing for all high traffic areas as required for a period of one year after soft opening.

FF&E安装前,对所有室内的建筑和装修用的大理石和石材进行打磨和表面处理。所有材料要复位到各自指定的位置。试运营开始后1年的时间内,按要求对人流量大的区域的石材进行打磨或抛光,每月一次。

e) Window Cleaning

窗户清洁

Provide for complete cleaning of all windows and architectural glass immediately prior to soft opening.

Provide quarterly cleaning of all exterior windows for a period of one year after soft opening.

在试营业前夕对所有窗户和建筑琉璃进行彻底清洁。试运营开始后1年的时间内,每季度一次对所有外部的窗户进行清洁。

f) Elevators

电梯

During the initial warranty period, provide for complete testing, adjusting and preventive maintenance of

all elevators. Provide emergency call back service during normal working hours at no additional cost. The

cost of all replacement parts and labour are to be included in the warranty and there shall be no allowance

charged to this contract. Contractor shall be responsible for local filing of all test reports and system

certifications that local authorities having jurisdiction require. Contract shall commence in conjunction with the one-year warranty from the date of soft opening.

在首个质保期内,对所有电梯进行测试、调整和保养。在正常工作时间免费提供紧急回拔服务。更换零件的费用和劳务费用包含在质保服务内,本合同不提供津贴。 承包人应负责提交当地主管机构所要求的测试报告和系统证书。合同与一年质保期同时在试营业开始的日期生效。

g) UPS Systems

UPS系统

Provide quarterly preventive maintenance and testing during normal working hours of all UPS electronics

and battery systems for a period of one year after soft opening. Contractor shall submit quarterly test

reports indicating operating conditions of all components. The cost of all replacement parts and lab our are

to be included in the warranty and there shall be no allowance charged to this contract.

试运营开始后1年的时间内,每季度在正常工作时间里为所有UPS电气进行一次保养。承包人应就所有元件的运行状况提交季度测试报告。更换零件的费用和劳务费用包含在质保服务内,本合同不提供津贴。

h) Telephone Switch Systems

电话总机

Provide preventive maintenance, testing and adjusting as per manufacturer recommendations, during

normal working hours, of all telephone switchgear and related systems for a period of one year after soft

opening. Cost of all replacement parts and labour are to be included in the warranty and there shall be

no allowance charged to this contract. Contractor shall submit quarterly test reports indicating operating

conditions of all components.

试运营开始后1年的时间内,在正常工作时间里根据生产商所建议的,对所有总机设备及相关系统进行保养、测试和调整。更换零件的费用和劳务费用包含在质保服务内,本合同不提供津贴。承包人应就所有元件的运行状况提交季度测试报告。

i) Building Management Systems

建筑物管理系统

Provide preventive maintenance, testing and adjusting as per manufacturer recommendations of all BMS

and related systems for a period of one year after soft opening. The cost of all replacement parts and

labour are to be included in the warranty and there shall be no allowance charged to this contract. Provide

twenty-four hours of training to be scheduled by the operator. Provide for upgrades to system software and

hardware to ensure that the system is per the latest revision at the end of the contract period. Contractor

shall, during the contract period, update or create new system graphics and programming as requested by

Four Seasons. Contractor shall provide remote support and system back up as required. Contractor shall

submit quarterly test reports indicating operating conditions of all components. Provide emergency callback service during normal working hours at no additional cost. Contract shall commence in conjunction with the one-year warranty from the date of soft opening.

试运营开始后1年的时间内,根据生产商所建议的,对所有整个建筑物管理系统(BMS)及相关系统进行保养、测试和调整。更换零件的费用和劳务费用包含在质保服务内,本合同不提供津贴。按照经营者的安排,提供24个小时的培训。为系统软硬件进行升级更新,保证在合同结束时整个系统是最新式的。承包人在合同期内应根据四季酒店的要求更新或制作新的系统图表和程序设计。承包人应按要求提供远程支持和备份系统。承包人每季度应就所元件的运行状况提交一份测试报告。在正常工作时间免费提供紧急回拔服务。合同与一年质保期同时在试营业开始的日期生效。

j) Fire Alarm and Security Systems

火警及安全系统

Provide preventive maintenance, testing and adjusting as per the manufacturer recommendations, local

codes of NFPA, whichever is more stringent of all fire alarm, life safety and security related systems for

a period of one year after soft opening. Cost of all replacement parts and labour is to be included in the

warranty and there shall be no allowance charged to this contract. Cost of lab our for the bi-annual testing

and calibration of all fire detection devices shall be charged to this contract. Provide twenty-four hours

of training to be scheduled by Four Seasons. Provide for upgrades to system software and hardware to

ensure that the system is per the latest revision at the end of the contract period. Contractor shall, during the contract period, update or create new system graphics and programming, as requested by Four Seasons.

试运营开始后1年的时间内,根据生产商所建议的,或当地国家防火协会(NFPA)所要求的(取两者中较严格的一个),对所有火警,救生和与安全相关的系统进行保养、测试和调整。更换零件的费用和劳务费用包含在质保服务内,本合同不提供津贴。本合同负责双年检测与校正火警装置的劳务费。按照四季酒店的安排提供24个小时的培训。为系统的软硬件进行升级更新,保证在合同结束时整个系统是最新式的。承包人在合同期内应根据四季酒店的要求更新或制作新的系统图表和程序设计。

Contractor shall provide remote support and system back up as required. Contractor shall submit quarterly

test reports indicating operating conditions of all components. The Contractor shall be responsible for all

local filings of test reports and system certifications that local authorities having jurisdiction require. This

contract shall commence in conjunction with the one-year warranty from the date of soft opening.

承包人应按要求提供远程支持和备份系统。承包人应就所有元件的运行状况提交季度测试报告。承包人应负责提交当地主管机构所要求的测试报告和系统证书。合同与一年质保期同时在试营业开始的日期生效。

k) Emergency/Standby Generators and Switchgear

应急/备用发电机和接电设备

Initial warranty period is to cover complete testing, adjusting and preventive maintenance of all power

generation/switching and fuel delivery systems. The cost of all replacement parts and lab our are to be

included in the warranty and there shall be no allowance charged to this contract. Contractor shall be

responsible for local filing of all test reports and system certifications that local authorities having jurisdiction require. This contract shall commence in conjunction with the one-year warranty, from the date of soft opening.

首个质保期应包含对所有发电机/接电设备和燃油输送系统的彻底测试,调整和保养。更换零件的费用和劳务费用包含在质保服务内,本合同不提供津贴。承包人应负责提交当地主管机构所要求的测试报告和系统证书。合同与一年质保期同时在试营业开始的日期生效。

l) Commercial Refrigeration and Air Conditioning Systems

商用电冰箱及空调系统

Provide quarterly preventive maintenance and adjusting during normal working hours of all refrigeration

and ice making systems for a period of one year after soft opening. Contractor shall submit quarterly test

reports indicating operating conditions of all components. Cost of all replacement parts and labour are to be included in the warranty and there shall be no allowance charged to this contract. Contract shall commence in conjunction with the one-year warranty from the date of soft opening.

试运营开始后1年的时间内,在正常工作时间里对所有冰箱与制冰设备进行保养和调整。承包人应就所有元件的运行状况提交季度测试报告。更换零件的费用和劳务费用包含在质保服务内,本合同不提供津贴。合同与一年质保期同时在试营业开始的日期生效。

m) Laundry Systems

洗衣房

Initial warranty period is to cover complete testing, adjusting and preventive maintenance of all laundry

equipment and systems as per the manufacturer recommendations. Service shall be provided on a biweekly basis for the purpose of greasing and adjusting all rotating or gas/steam/electric fired equipment.

Provide forty hours of training on laundry systems, which will be scheduled by Four Seasons. Cost of all

replacement parts and lab our are to be included in the warranty and there shall be no allowance charged

to this contract. Contract shall commence in conjunction with the one-year warranty from the date of soft

opening.

首个质保期应包含,根据生产商所建议的,对所有洗衣房设备和系统的彻底测试,调整和保养。每两个星期对所有旋转或燃气/蒸汽/电加热设备进行加油和调整。按照四季酒店的安排就洗衣系统提供40个小时的培训。更换零件的费用和劳务费用包含在质保服务内,本合同不提供津贴。合同与一年质保期同时在试营业开始的日期生效。

n) Kitchen Systems

厨房

Initial warranty period to cover complete testing, adjusting and preventive maintenance of all kitchen

equipment and systems (except refrigeration) as per the manufacturer recommendations. Service shall

be provided on a bi-weekly basis for the purpose of adjusting all rotating, gas fired, steam fired and other

equipment so as to maintain the equipment. Provide forty hours of training on equipment, which will be

scheduled by Four Seasons. Cost of all replacement parts and labour is to be included in the warranty

and there shall be no allowance charged to this contract. Contract shall commence in conjunction with the

one-year warranty from the date of soft opening.

首个质保期应包含,根据生产商所建议的,对所有厨房设备和系统(冰箱除外)的彻底测试,调整和保养。每两个星期对所有旋转设备、燃气加热设备、蒸汽加热设备和其它设备进行调整和保养。按照四季酒店的安排就洗衣系统提供40个小时的培训。更换零件的费用和劳务费用包含在质保服务内,本合同不提供津贴。合同与一年质保期同时在试营业开始的日期生效。

o) Pool/Spa Systems/Water Features

泳池/水疗系统/水布景

Initial warranty period is to cover complete testing, adjusting and preventive maintenance of all pool and

spa filtration and chemical treatment systems. The cost of all replacement parts and lab our are to be

included in the warranty and there shall be no allowance charged to this contract. Provide eight hours of

system training to be scheduled by Four Seasons. Contractor shall be responsible for local filing of all test

reports and system certifications that local authorities having jurisdiction require. Contract shall commence in conjunction with the one year warranty from the date of soft opening.

首个质保期应包含对所有泳池、水疗系统和化学处理系统的彻底测试,调整和保养。更换零件的费用和劳务费用包含在质保服务内,本合同不提供津贴。按照四季酒店的安排就洗衣系统提供8个小时的系统培训。承包人应负责提交当地主管机构所要求的测试报告和系统证书。合同与一年质保期同时在试营业开始的日期生效。

P) Water Treatment

水处理

Provide bi-weekly testing of all open and closed HVAC water distribution systems. Provide quarterly

laboratory analysis of systems chemical levels and corrosion rates on coupons. Provide a one-year supply

of all required chemicals to accomplish water treatment as per the manufacturer recommendations of the

various HVAC systems. Provide for one complete cleaning, descaling and disinfection of open systems.

Provide sixteen hours of training to be scheduled by Four Seasons and assist in certifying operator’s

employees if required by local authorities. Contractor shall be responsible for local filing of all test reports

and system certifications that local authorities having jurisdiction require. Contract shall commence in

conjunction with the one-year warranty from the date of soft opening.

每两星期对所有开放式或封闭式的暖通水分送系统进行一次测试。每季度免费提供关于系统的化学成份水平和腐蚀率的实验分析。对所有制造商建议的用于各式HVAC系统进行水处理的化学品,提供一年的使用量。对开放式系统进行一次彻底的清洁、除锈、消毒处理。按照四季酒店的安排提供16个小时的培训,或者在当地机关要求时,帮助经营者的雇员取得认证。承包人应负责提交当地主管机构所要求的测试报告和系统证书。合同与一年质保期同时在试营业开始的日期生效。

q) Central Chillers

中央空调

Initial warranty period to cover complete testing, adjusting and preventive maintenance of all central chiller systems as per the manufacturer recommended schedule. Provide for one complete eddy current test of all chiller tubes and one annual cleaning of the tubes and water boxes. Work is to be scheduled by

Four Seasons as dictated by the seasonal demand for cooling. Cost of all replacement part and labour

is to be included in the warranty and there shall be no allowance charged to this contract. Contractor

shall be responsible for local filing of all test reports and system certifications that local authorities having jurisdiction require. Contract shall commence in conjunction with the one-year warranty from the date of soft opening.

首个质保期应包含,根据生产商所建议的程序,对所有中央制冷系统的彻底测试,调整和保养。对所有制冷管道进行一次彻底的涡流测试,并每年清洁管道和承水盒。四季酒店将根据不同季节对制冷的需求进行工作安排。更换零件的费用和劳务费用包含在质保服务内,本合同不提供津贴。承包人应负责提交当地主管机构所要求的测试报告和系统证书。合同与一年质保期同时在试营业开始的日期生效。

r) MATV and Sound Systems

主天线电视及音响系统

Provide for testing, adjustments and rebalancing of distribution systems as per the manufacturer

recommended schedules, but no less than two service visits during the one-year period. Cost of all

replacement parts and lab our is to be included in the warranty and there shall be no allowance charged

to this contract. Provide sixteen hours of system training to be scheduled by Four Seasons. Contract shall

commence in conjunction with the one-year warranty from the date of soft opening.

根据生产商所建议的程序,对所有配线系统进行测试,调整和重新协配,在每一年内,服务次数不得少于两次。更换零件的费用和劳务费用包含在质保服务内,本合同不提供津贴。按照四季酒店的安排提供16个小时的系统培训。合同与一年质保期同时在试营业开始的日期生效。

s) Fire Suppression Systems

灭火系统

Initial warranty period to cover complete testing, adjusting and preventive maintenance of all pre-action or

dry chemical, or Ansul fire suppression systems. Cost of all replacement parts and lab our are to be included in the warranty and there shall be no allowance charged to this contract. Contractor shall be responsible for local filing of all test reports and system certifications that local authorities having jurisdiction require. Contract shall commence in conjunction with the one-year warranty from the date of soft opening.

首个质保期应包含对所有预作用灭火系统、干燥化学品或安索(Ansul)灭火系统或的彻底测试,调整和保养。更换零件的费用和劳务费用包含在质保服务内,本合同不提供津贴。承包人应负责提交当地主管机构所要求的测试报告和系统证书。合同与一年质保期同时在试营业开始的日期生效。

t) Fire Pumps and Delivery Systems

消防泵及送水系统

Perform one annual maintenance and testing by certified Contractor so as to comply with NFPA 20. Contractor shall be responsible for local filing of all test reports and system certifications that local authorities having jurisdiction require.

每年由合格的承包人进行一次维护和测试,以达到国家防火协会的NFPA20的要求。承包人应负责提交当地主管机构所要求的测试报告和系统证书。

u) Water Storage Systems

储水系统

Provide for one cleaning and disinfections of all wood or metal domestic water storage tanks. Provide

laboratory analysis of water samples to ensure water supply and storage facilities are safe. Contractor

shall be responsible for local filing of all test reports and system certifications that local authorities having

jurisdiction require. Allowances are to be made for this work to be completed after hours. Work will be

scheduled by Four Seasons.

对所有木制或金属储水箱进行一次清洁和消毒。提供水样的实验室分析,以保证供水与储水设施的安全。承包人应负责提交当地主管机构所要求的测试报告和系统证书。对需在下班后继教完成的工作提供津贴。工作与四季酒店安排。

v) Kitchen Exhaust Systems

厨房排气系统

Perform quarterly (or more frequent if required by code) cleaning and degreasing of all horizontal ductwork. Clean and degrease all fans, blower and deodorizing or smoke containment systems. Contractor shall be responsible for local filing of all test reports and system certifications that local authorities having jurisdiction require. Allowances are to be made for this work to be completed after hours and will be scheduled by the operator. Contract shall commence in conjunction with the one-year warranty from the date of soft opening.

每季度(如法规另有要求,应更频繁地)对所有水平管道系统进行清洁和润滑。对所有风扇、送风机、除臭和吸烟系统进行清洁和润滑。承包人应负责提交当地主管机构所要求的测试报告和系统证书。经营者将对需在下班后继教完成的工作安排津贴。合同与一年质保期同时在试营业开始的日期生效。


11 . SHOP DRAWING SUBMITTALS

呈交施工图

a) Contractor Submittal Responsibility

承包人呈交施工图的责任

Four Seasons will review select shop drawing submittals to ensure that quality, durability and operational

efficiency have been addressed. This review is in addition to that of the appropriate Consultant. Comments

noted by Four Seasons will be incorporated onto the shop drawings after having been reviewed by

Consultant.

四季酒店将抽样检查呈交的施工图,以确保设计考虑了质量、耐用性的运作效率。四季酒店的检查与顾问的检查是不同的。四季酒店提出的意见,经顾问评议后将纳入施工图。

The Shop Drawing Submittals Matrix is based on National Master specification divisions. Submittals to be sent to Four Seasons are indicated in the left column.

施工图呈交表是按照《国家主要规格》制作的。需要呈交四季酒店的在左栏标出。

b) Shop Drawing Submittal Matrix

施工图呈交表

DESIGN STANDARDS设计标准